Client: QBS International
Duration: 2 years
Scope: Dewatering
Project Details:
Dewatering was required for a total of 7 shafts measuring 10m x 10m up to a maximum depth of 17m below the existing ground level. Dewatering was carried out using a deepwell system, consisting of electrical borehole pumps with a total systems capacity of 700 m3/hr. Discharge was directly to the sea through a 4.9km HDPE discharge network installed managed by UH.